冷再生機(jī)出租之水泥改良土施工流程
來(lái)源:http://m.gzmilo.com/ 日期:2021-07-30 發(fā)布人:
一、適用范圍
1、 Scope of application
冷再生機(jī)出租為保證路床厚度范圍內(nèi)的CBR值和壓實(shí)度達(dá)到規(guī)范要求,全線路床上部36cm厚采用6%水泥土處理。針對(duì)低填淺挖路基,當(dāng)路基填方高度或挖方深度≤155cm時(shí),路床下部44cm厚換填4%的水泥土處理,路床上部36cm厚換填6%水泥土處理。
In order to ensure that the CBR value and compactness within the thickness range of the roadbed meet the specification requirements, the 36cm thick upper part of the roadbed of the whole line is treated with 6% cement soil. For low fill and shallow excavation subgrade, when the subgrade filling height or excavation depth is ≤ 155cm, the 44cm thick lower part of the roadbed shall be replaced with 4% cement soil, and the 36cm thick upper part of the roadbed shall be replaced with 6% cement soil.
二、作業(yè)準(zhǔn)備
2、 Job preparation
1、冷再生施工租賃場(chǎng)地準(zhǔn)備
1. Preparation of rental site for cold regeneration construction

(1)直接填筑的路基基底,施工前必須通過(guò)審查簽證;需要進(jìn)行地基處理的基底必須完成各項(xiàng)處理,并滿足地基處理的要求。
(1) The subgrade base directly filled must pass the examination and visa before construction; For the base requiring foundation treatment, various treatments must be completed and meet the requirements of foundation treatment.
(2)場(chǎng)地應(yīng)該保證足夠的平整度,滿足設(shè)備、人員進(jìn)場(chǎng)要求。
(2) The site shall ensure sufficient flatness to meet the mobilization requirements of equipment and personnel.
(3)做好場(chǎng)地的臨時(shí)排水和防雨措施。按照施工運(yùn)量和施工機(jī)械的大荷載修筑施工便道。
(3) Take temporary drainage and rainproof measures for the site. The construction access road shall be built according to the construction traffic volume and the large load of construction machinery.
2、技術(shù)準(zhǔn)備
2. Technical preparation
做好相關(guān)人員的技術(shù)培訓(xùn)和技術(shù)交底工作,使參加施工的全體人員充分認(rèn)識(shí)高速鐵路路基填筑的關(guān)鍵技術(shù)、質(zhì)量控制要點(diǎn)。
Do a good job in technical training and technical disclosure for relevant personnel, so that all personnel participating in the construction can fully understand the key technologies and quality control points of subgrade filling of high-speed railway.
3、勞動(dòng)力、機(jī)械設(shè)備配置
3. Allocation of labor force and mechanical equipment
人員、機(jī)械設(shè)備應(yīng)根據(jù)施工方案組合工期要求進(jìn)行合理的配置。路堤填筑區(qū)為一個(gè)完整的作業(yè)區(qū),每個(gè)作業(yè)區(qū)人員配置:施工隊(duì)長(zhǎng)1名,領(lǐng)工員2名,指揮卸土位置人員2名,測(cè)量及試驗(yàn)檢測(cè)人員4~6人,其他機(jī)械工、普工20~30人。
The combination of machinery and equipment shall be reasonable according to the requirements of construction period. The embankment filling area is a complete operation area, and the staffing of each operation area is: 1 construction team leader, 2 foremen, 2 personnel directing the unloading position, 4 ~ 6 measurement and test personnel, and 20 ~ 30 other mechanics and general workers.
根據(jù)施工需要,每個(gè)作業(yè)面配備反鏟挖掘機(jī)一臺(tái)、宣化-140推土機(jī)一臺(tái)、YZ-22振動(dòng)壓路機(jī)兩臺(tái)、天工-160平地機(jī)一臺(tái),徐工-230灰土拌和機(jī),自卸運(yùn)輸車6輛,撒水車一臺(tái)備用。當(dāng)運(yùn)距較遠(yuǎn)時(shí),自卸車的數(shù)量可適當(dāng)增加
According to the construction needs, each working face is equipped with one backhoe excavator, one xuanhua-140 bulldozer, two yz-22 vibratory rollers, one tiangong-160 grader, xcmg-230 lime soil mixer, 6 dump trucks and one sprinkler for standby. When the transportation distance is long, the number of dump trucks can be increased appropriately
閱讀/ Recommended reading
- 水泥撒布車的知識(shí)特點(diǎn)介紹 2025-02-28
- 冷再生機(jī)是一種、多用途的道路施工 2025-02-25
- 冷再生機(jī):土壤穩(wěn)定路拌施工的優(yōu)選設(shè)備 2025-02-22
- 冷再生機(jī)液壓油的作用 2025-02-17
冷再生機(jī)操作規(guī)程
[2018-08-23]
冷再生機(jī)的操作規(guī)程是確保操作人員和設(shè)備的重要指導(dǎo)原則。以下是冷再生機(jī)操作規(guī)程的詳細(xì)內(nèi)容: The safety operating procedures for...